Please find below some of the highlights from Turceni

  • Main Electrical Building with 2583m2 construction area handed over to Siemens on 15.02.2010
  • Gypsum Dewatering Building +25.55 level slab (1010 m2) concrete is poured successfully on 19.05.2010. Vacuum Belt Filters are installed by AEE on +25.55 level.
  • Foundations of 1000 m long Process Water Pipe Bridge are handed over to AEE for installation of pipes in March 2010.
  • Foundations of 311 m long Cable Bridge are handed over to AEE for installation of cables in April 2010.
  • Foundations of 158 m long Bagger Bridge are handed over to AEE for installation of pipes in May 2010.
  • 5th partition of Absorber Unit 6 cast on 16.06.2010 completing in total 2040 m3 of concrete.
  • One of the main Buildings in Turceni Project, Limestone Storage Building, is delivered to AEE for steel erection on 19.06.2010. Limestone Storage Building contains 6700 m2 formworks, 4900 m3 concrete and 892 tons of reinforcement work.
  • Micro Piling work has been performed at Absorber 4 Flue Gas Duct foundation in June 2010.

Fashion House Outlet Center

The 28,000 square - eter project will have 140 store units, 2,700 parking ... Read more

DSV Warehouse

In 2007 DSV Group took over Frans Maas Company, his local name becoming ... Read more

ProLogis

ProLogis is a leading global provider of distribution facilities and services, ... Read more